720 sq ft of interior wall and ceiling crack repairs throughout a three-bedroom unit. The reconstruction included new insulation, drywall, and finishing to restore the unit to its original condition and improve interior performance.
Project Duration: Approximately 3 Weeks
Key challenges overcome:
● Lead-Based Paint: Required full compliance with EPA (RRP) Lead-Safe Work Practices. We utilized strict containment, dust control, and HEPA cleaning throughout the demolition and preparation phases.
● Furnished Unit Logistics: Executed a meticulous, phased, room-by-room approach in a fully furnished unit. We carefully protected the space and coordinated the workflow to ensure efficient progress.