2,800 sq ft of waterproofing across four elevated patios and stair landings. We installed a new system and L-flashing to enhance long-term weather protection and overall building envelope performance.
Project Duration: Approximately 4 Weeks
Key challenges overcome:
● Up-to-Code Upgrades: Installed all systems in strict accordance with manufacturer specifications and the California Building Code.
● Lead-Safe Practices: Safely managed exterior stucco demolition under full EPA RRP compliance, utilizing proper containment and dust control.
● Multi-Contractor Coordination: Seamlessly sequenced specialty contractors and inspections to maintain safe conditions and stay on schedule.
● Occupied Life-Safety: Phased work on emergency exit patios one-half at a time to guarantee residents always had unobstructed egress.